thermorema f Short Description
OWNER: SHPP THERMOREMA S.A.
PROJECT: CONSTRUCTION OF 1.950MWe SMALL HYDROELECTRIC POWER PLANT
LOCATION: SPERCHIADA, FTHIOTIDA PREFECTURE, GREECE

  Description:   Services:
Small HydroElectric Power Plant – 1.95MWe
- Plant production start: 2003
  • Feasibility – Financial Studies
  • Design – Licensing
  • Selection and procurement of electrical production electromechanical equipment
  • Project Management
   Scope of work:    Technical Data:
  • TURN KEY construction
  • Intake: Civil works, equipment procurement/construction of electromechanical installations
  • Penstock: Complete installation of GRP penstock, manufacturing of special parts
  • Power House: Civil works, installation of electrical production equipment, manufacturing of penstock special parts and parts of electromechanical equipment
  • Three (3) horizontal axis Pelton turbines, with two (2) noozles, manufactured by Gilkes (England), 680kW output each
  • Three (3) synchronous generators, 400V, 50Hz, 3-phase, 1250kVA output each
  • GRP (Glassfiber Reinforced Plastic) Penstock, diameter: DN900-DN800, length 6400m in total
 BIENTER S.A. shareholders’ project